CO-OP Motherwell

Key activity

Cold Store and Plant Room Installation

Client

EJM Engineered Systems Limited

Project

CO-OP Distribution Centre

Details

Working for EJM Engineered Systems Limited at the CO-OP distribution centre at Motherwell we undertook a huge installation for a cold store and plant room installation including the solving the problem of very complex pipe runs and the off-site manufacture of 70% of pipe work. The contract included 100% NDT inspection, transportation of pipe work spools from our workshop to Denmark to be pre-insulated and delivered to site ready for assembly to meet the client's fast-track programme.

http://www.ejmrefrigeration.co.uk/