Mechanical Installation

case studies

Buttershaw High School

Key activity

Mechanical Installation

Client

Lorne Stewart Costain Ferovial

Project

Buttershaw High School Bradford

Year

2008

Details

We were set a tough assignment by Lorne Stewart Costain Ferovial at Buttershaw High School Bradford, to design a plant room ‘in a box’ and to off-site manufacture it in our workshop including skid units, comprising of boiler skids and pumps and low loss header skids, taking into consideration the physical elements of an existing boiler house.

This ‘plant room in a box’ was delivered to site and the complete interconnecting pipework was installed in under three weeks, resulting in minimum disruption on site.



http://www.lornestewart.com/WesternDivision.htm