CASE STUDY

Weekend work

Key Activity

Off site fabrication

Client

Sure Solutuons

Project

Gadbrooks

Year

2019

Details

Offsite valve stations

A site near Northwich required a weekend changeover of a chiller system and its control valves. A site visit and some measurements later the valve stations and frame were manufactured off site, transported and lifted in halving the onsite install time. The client and end user were very happy.